County News
Back into the pool
Small steps after a long stalemate
Wellington is out of wastewater capacity. As such, it cannot grow. No new homes or businesses can be built until the municipality expands the treatment plant. Shire Hall has little choice but to press ahead, despite a troubled waterworks construction record: every component of its 2021 Wellington master servicing plan has run over budget and behind schedule.
It must press ahead.
Shire Hall expects to complete the design for the Wellington wastewater treatment plant expansion early in 2027 and present it at a public meeting in the first quarter of the year. With council’s blessing, tenders could be issued soon afterward, with construction to follow.
The total project cost is currently estimated at $55 million. The federal government has committed $20 million toward the expansion.
BACKGROUND
Built in 1975, Wellington’s wastewater treatment plant was designed to process 1,500 cubic metres of village effluent a day. Average daily flows have rarely exceeded 55 per cent of its rated capacity, but heavy rain events periodically push the plant to its limit.
Wellington’s wastewater bottleneck is not simply a matter of treatment capacity—it is a matter of who controls it. Last year’s capacity review highlighted an existing bind: one developer holds the plant’s remaining capacity (apart from an allocation for 40 potential affordable homes on the former Dukedome site).
For the municipality, the only reasonable course is to build. Waiting would leave other builders—and Wellington’s growth—dependent on one developer’s timetable. Expanding the plant will provide capacity for new homes and businesses to proceed, rather than leaving the village’s future on hold.
The developer may eventually build, but Wellington cannot afford to wait indefinitely.
NEW OR EXPANDED?
Shire Hall reports that the detailed design of the wastewater plant expansion is about 60 per cent complete. The design includes “the majority of the existing WWTP components being retained and incorporated into the expanded facility”.
Shire Hall is exploring ways to phase the expansion based on lower expectations for population growth generally in Prince Edward County.
THE PRICE TAG
The 2021 Master Servicing Plan, which mapped out the expansion of Wellington’s waterworks, estimated the new wastewater treatment plant would cost $27.7 million. The current estimate is $55 million—nearly twice that amount. It includes a construction contingency, contract administration, materials testing and County staff time.
The question is how closely that estimate will hold when tenders come in. Shire Hall acknowledges that tendered prices on other projects have consistently exceeded the plan’s estimates. The water tower ultimately cost 60 per cent more than originally estimated, while the trunklines project is already more than double its 2021 estimate.
For Shire Hall’s new leadership, this is a chance to put past cost overruns behind it and deliver a more predictable outcome.